2023 - MMSD Brown Deer Road Construction

Public Open House: December 5, 2022

There will be a Public Open House at the Bayside Village Hall on December 5, 2022 with the meeting starting at 6:00pm.  Learn more about the Brown Deer Road project.  There will be an opportunity to ask questions about the project.  Below is the flyer with  more information.

Brown Deer Road Public Open House Flyer


Update:  November 3, 2022 

Work on  the MMSD Brown Deer Road project is scheduled to start January 2023.  Below are the contractor proposed timelines for traffic control and detours during this project. 

Stage 1 – January/ February – south side of Brown Deer Road closed.  2 lanes of traffic open on north side of roadway.

Stage 2 – March - Regent Road closed at intersection, south side of Brown Deer Road closed.  2 lanes of traffic open on north side of roadway.

Stage 3 – April – Regent Road closed at intersection, Brown Deer Road closed, - Garden Center/ resident access from the West. Port Washington Road and Green Tree Road detour will be utilized. 

Stage 4  - April/ May– Regent Road closed at intersection, Brown Deer Road closed, - Garden Center/ resident access from the East.  Port Washington Road and Green Tree Road detour will be utilized.

June and July will include final restoration and backfilling of the shaft at regent road and will include stage 2 and later stage 1 traffic control.  The stages are bit fluid as construction progresses; however, the full closure of the roadway is limited to 80 calendar days which includes the restoration of the roadway. 

If you want more details about this project, the link below will take you to the MMSD project site.

 https://www.mmsd.com/what-we-do/wastewater-treatment/sewers/brown-deer-road-sanitary-sewer-replacement

Below is the contractor traffic control plan.

Brown Deer Rd Traffic Control Plan


Update August 16, 2022- Village staff was notified by the Milwaukee Metropolitan Sewerage District that it will be installing a new sanitary sewer in Brown Deer Road between Regent Road and the railroad tracks beginning in September 2022.  During the first two stages of work between September 6 and December 5, Brown Deer Road and Regent Road is anticipated to remain open to through traffic.  During phases 3 and 4 (December through early February), it is anticipated that the intersection of Brown Deer and Regent Roads will be completely closed to all through traffic.  Detours will be in place to route through traffic around the construction.  Fox Point Village staff has already informed MMSD that the detours should not be Dean, Bradley or Calumet Roads.  

Construction Schedule:

Brown Deer Preliminary Schedule